April 2009 Olin and design team begin schematic design phase
May 2009 Construction begins on interim clearing and planting. New sod and grass will be planted so that the community can enjoy the area while the Park’s design is completed.
June 2009 Interim clearing and planting completed.
December 2009 New Park design complete.
January / February 2010 Construction bidding and permitting.
March 2010 Major construction to begin.
March 2011 Park opens to the public.